Press Release

PUC Approves Long-Term Infrastructure Improvement Plans, Distribution System Improvement Charges for UGI Central Penn, UGI Penn Natural

Published on 9/11/2014

Filed under: Gas

HARRISBURG – The Pennsylvania Public Utility Commission (PUC) today approved the long-term infrastructure improvement plans (LTIIP) and plans to implement distribution system improvement charges (DSIC) for UGI Penn Natural Gas Inc. (UGI-PNG) and UGI Central Penn Gas Inc. (UGI-CPG).

The Commission voted 5-0 to approve the companies’ LTIIPs and DSICs, which were filed in compliance with Act 11 of 2012. 

UGI-PNG

The UGI-PNG LTIIP is a five-year plan that allows UGI-PNG to replace an average of 17 miles of pipeline per year.  Further, UGI-PNG plans to spend nearly $23 million per year on pipeline replacements, service line improvements, and safety device installations, over the five-year period of the plan. The company’s DSIC mechanism may be implemented once the company files a tariff. However, some issues related to the DSIC were referred back the PUC’s Office of Administrative Law Judge (OALJ) for further hearings. As a result of the commitments made in a 2012 Settlement Agreement regarding a 2011 fatal natural gas explosion in Allentown, Pa., UGI-PNG cannot recover money through the DSIC until April 1, 2015.

UGI-PNG provides service to approximately 160,800 customers in 13 counties in northeastern Pennsylvania.

UGI-CPG

The LTIIP will allow UGI-CPG to replace an average of over 17 miles of pipeline per year during the five-year period of the LTIIP.  Further, UGI-CPG plans to spend nearly $14 million per year on pipeline replacements, service line improvements, and safety device installations, over the five-year period of the plan. The company’s DSIC mechanism may be implemented once the company files a tariff. However, some issues related to the DSIC were referred back the OALJ for further hearings. As a result of the commitments made in a 2012 Settlement Agreement regarding a 2011 fatal natural gas explosion in Allentown, Pa., UGI-PNG cannot recover money through the DSIC until April 1, 2015.

UGI-CPG provides natural gas service to approximately 76,500 customers in 33 counties across Pennsylvania.

Act 11 requires among other things that utilities file LTIIPs as part of any action to establish a DSIC to recover reasonable and prudent costs incurred to repair, improve or replace certain eligible distribution property that is part of a utility’s distribution system.

As of Jan. 1, 2013, public utilities could petition the Commission for approval to establish a DSIC. The petition must contain the following elements: 1) an initial tariff; 2) testimony and exhibits to demonstrate that the DSIC will ensure the provision of adequate, efficient, safe, reliable and reasonable service; 3) a long-term infrastructure plan; 4) certification that a base rate case has been filed within the past five years; and 5) any other information required by the Commission.  The petition must demonstrate that granting the petition and allowing the DSIC to be charged will accelerate the replacement of infrastructure.

On Feb. 14, 2012, Governor Corbett signed Act 11 of 2012, which allows jurisdictional water and wastewater utilities, natural gas distribution companies, city natural gas distribution operations, and electric distribution companies to petition the Commission for approval to implement a DSIC. Under the law, the DSIC must be designed to provide for "the timely recovery of the reasonable and prudent costs incurred to repair, improve or replace eligible property in order to ensure and maintain adequate, efficient, safe, reliable and reasonable service.”

The Pennsylvania Public Utility Commission balances the needs of consumers and utilities; ensures safe and reliable utility service at reasonable rates; protects the public interest; educates consumers to make independent and informed utility choices; furthers economic development; and fosters new technologies and competitive markets in an environmentally sound manner.

For recent news releases and video of select Commission proceedings or more information about the PUC, visit our website at www.puc.pa.gov. Follow the PUC on Twitter – @PA_PUC for all things utility.  “Like” PAPowerSwitch on Facebook for easy access to information on electric shopping.

# # #

Docket No. P-2013-2347340

 

 

 

 

Contact:

 

Complaints

Learn how to submit a complaint with a public utility. You can also search existing formal complaints.

Get Details

Subscribe to Press Releases

Keep track of PUC news and activities with press releases delivered straight to your email inbox.

Subscribe

Need More Help?

If you can't find what you're looking for here, please contact the PA Public Utility Commission. Call us at 1-800-692-7380 or contact us online.

Document Search

Public utility documents available electronically include case dockets, public meeting orders and more.

Filing & Resources

Find utility-related reports, laws and regulations, federal filings, tariffs, procedures and more.

eFILING

Consumers, utilities and attorneys can save time by submitting documents to the PUC electronically.