Skip to content

Utility Code 110500

The Utility Detail View displays the Utility Information (identified by Utility Code - 110500), authorities, and case information associated with that utility.

Utility Information

Basic Utility Information

Utility Name
PPL ELECTRIC UTILITIES CORP

Utility Code
110500

Utility Type
Electric

Utility Status
Active

Carrier ID

Utility Contact Information

Physical Address

Mailing Address
TWO NORTH NINTH STREET
ALLENTOWN PA 18101

Phone
610-774-5696

Fax
610-774-4102

Website
www.pplweb.com

Email
KKLOCK@PPLWEB.COM

Authority Information

Utility Authorities Information

Service Type Authority Status Date Certified Suspension Date Suspension Expiration Application Number Trading As Name
Electric Distributor Active A-110500 PPL UTILITIES (PPL)
Insurance Information

Utility Insurance Information

No insurance information for this utility.

EGS Territories

EGS Territories Serviced by a Utility

Residential
No

Citizens’ Electric
No

Small Commercial

Duquesne Light
No

Mixed Meter

Met-Ed
No

Large Commercial
No

PECO
No

Industrial
No

Penelec
No

Governmental
No

Penn Power
No


Pike
No


PPL
No


UGI Utilities - Electric
No


Wellsboro
No


West Penn Power
No

Docketed Cases

Docket Number Case Status Date Filed Allegation
A-110500F0277 Closed 1/21/1999 LETTER OF NOTIFICATION OF PP&L, INC. FILED PURSUANT TO 52 PA. CODE CHAPTER 57 WITH RESPECT TO THE LINGLESTOWN 138/69 KV LINE RELOCATION.
U-00994286 Closed 1/25/1999 AGREEMENT DATED FEBRUARY 9, 1998, BETWEEN PP&L, INC., AND THE BOROUGH OF WYO- MISSING HILLS, RELATIVE TO THE RIGHT TO CONSTRUCT, OPERATE AND MAINTAIN ELEC- TRIC LINE FACILITIES IN THE BOROUGH OF WYOMISSING HILLS, COUNTY OF BERKS, COMMONWEALTH OF PENNSYLVANIA.
Z-00530374 Closed 1/25/1999 COMPLAINANT STATES THAT THEY FELL A LITTLE BEHIND WITH BILL WHENEVER THEY HAD TO UNEXPECTEDLY INCUR MOVING COSTS TWO TIMES WITHIN A SIX MONTH TIME FRAME. SHE HAS HAD TWO BRAIN SURGERIES AND FOLLOWED BY A CAR ACCIDENT WHICH LEFT HER WITH INJURIES. SHE HAS UNCEASING MEDICAL BILLS SHE HAD TO LEAVE HER JOB AS A NANNY BECAUSE OF HER HEALTH.
Z-00525105 Closed 1/26/1999 COMPLAINANT STATES THAT HE LIVES IN THE HOUSE BY HIMSELF, THERE USED TO BE FOUR PEOPLE, HE WOULD ALSO LIKE TO HAVE HIS LINE OR METER CHECKED HE DOESN'T AGREE WITH THE KILLOWATTS. AND WOULD LIKE A NEW BUDGET PLAN BASED ON CURRENT AVERAGE USAGE. HE IS IN THE MIDDLE OF A DIVORCE, AND JUST GETTING BY ON ESTABLISHING A NEW BUDGET PLAN BASED ON AVERAGE USAGE
C-00992108 Closed 1/28/1999 COMPLAINANT LIVES ON A FIXED INCOME AND HE PAYS 50% OF HIS INCOME TO RENT, HE CAN'T AFFORD TO MAKE THE PAYMENT REQUIRED OF $330.00 FROM GOV. ASSISTANCE. BENEFITS AND OWE MONTHLY RENT OF $295.00 HE ONLY HAS $35.00 LEFT TO LIVE OFF OF. THE COMPANY WANTED HIM TO PAY $46.00 A MONTH, BUT HE CAN'T AFFORD THAT.
Z-00534111 Closed 1/28/1999 COMPLAINANT IS ON DISABILITY AND ALL MONEY HE RECEIVES NOW IS GOING TO PAY PRE-EXISTING BILLS AND FEDERAL INCOME TAXES. HE HAS ELECTRIC HEAT AND A HEALTH PROBLEM (RESPERATORY) AND WOULDN'T LIKE HIS ELECTRICITY TURNED OFF.
U-00994290 Closed 1/28/1999 AGREEMENT DATED DECEMBER 1, 1998, BETWEEN PP&L, INC., AND THE CITY OF WILKES- BARRE, RELATIVE TO INSTALLATION OF EIGHT DECORATIVE LIGHTING CONTROL UNITS ON FOUR EXISTING WOOD POLES LOCATED ON SCOTT STREET, BLACKMAN STREET, PARK AVE- NUE AND SHERMAN STREET, IN THE CITY OF WILKES-BARRE, LUZERNE COUNTY, PENNSYL- VANIA.
C-00992104 Closed 1/28/1999 COMPLAINANT WHO IS VICE PRESIDENT OF AURORA ENTERPRISES INC, HAS COMPLAINTS AGAINST PP&L, SAYING THEY NEVER SHOWED HER WHERE METERS OR HOW MANY ACCOUNTS WERE AT THIS LOCATION. PP&L SENT PAST DUE NOTICES AFTER AURORA CLOSED ON THE PROPERTY, AND PP&L SHOULD CEASE ALL SERVICE IN THE NAME OF AURORA ENTERPR ISES.
U-00994288 Closed 1/28/1999 AGREEMENT DATE NOVEMBER 3, 1998, BETWEEN PP&L, INC., AND THE BOROUGH OF EMMA- US, RELATIVE TO THE INSTALLATION OF THREE DECORATIVE LIGHTING CONTROL UNITS ON THREE EXISTING POLES LOCATED ON CHESTNUT STREET, EMMAUS, LEHIGH COUNTY, PENNSYLVANIA.
C-00992119 Closed 2/2/1999 COMPLAINANT STATES THAT PP & L UNWARRNATED DELAY IN PLACING C & D TECHNOLOGI- ES INC ON A RATE SCHEDULE IS-P.
C-00992120 Closed 2/2/1999 COMPLAINANT STATES THAT THEY HAD CONTRACT WITH PP&L TO USE RATE SCHEDULE LP-4, AND ON OCTOBER 5, 1995 REPLACED ITS INTERRUPTIBLE POWER OPTION UNDER RATE SCHEDULE LP-4 WITH A INTERRUPTIBLE POWER TARIFF KNOWN AS RATE SCHEDULE IS-P
A-110500F0278 Closed 2/2/1999 APPLICATION OF PP&L, INC., FOR APPROVAL OF THE TRANSFER BY SALE OF PROPERTY, KNOWN AS PP&L'S OLD WEST SHORE CREW QUARTERS LOCATED IN HAMPDEN TOWNSHIP, CUMBERLAND COUNTY, PENNSYLVANIA, TO ALLISON MINER AND RACE MINER, C/O TWO-WAY TRAFFIC, INC.
Z-00536769 Closed 2/2/1999 COMPLAINANT IS CURRENTLY NOT WORKING AND THE $283.00 PER MONTH RIGHT NOW IS TOO MUCH.
C-00992121 Closed 2/2/1999 COMPLANANT STATES THEY HAD A CONTRACT WITH PP&L FOR OPTIONAL INTERRUPTIBLE SERVICE UNDER RATE SCHEDULE IS-P, AND SHOP VAC CLAIMS THAT PP&L HAS ADMINIS- TERED ASSESSMENT OF PENALTY AGAINST THEM, IN SUCH A WAY AS TO PROVIDE PP&L WITH A SUBSTANTIAL WINDFALL AT THE EXPENSE OF SHOP VAC
C-00992123 Closed 2/4/1999 COMPLAINANT STATES SHE HAD A CONTRACT TO PAY $15 IN ADDITION TO MY MONTHLY BILL ONE MONTH I MISS READ THE BILL AND MADE THE BILL OUT FOR $80, THEY KEPT SENDING NOTICES OF SHUT OFF AND I DIDN'T EVEN KNOW WHY BECAUSE I HAD MADE THE PAYMENT. COMPLAINANT WOULD LIKE TO GET PUT BACK ON HIS MONTHLY CHARGE PLUS $15.
C-00992129 Closed 2/5/1999 COMPLAINANT WOULD LIKE TO GET A PAYMENT PLAN, HE RECEIVED THEIR DECISION IN WHICH HE WAS TO PAY $188 PLUS $100 EXTRA PER MONTH. THAT IS WAY ABOVE HIS BUDGET. IN THE INTERUM I CAME TO A BUDGET WITH PP&L OF ONLY $188 PER MONTH.
C-00992137 Closed 2/8/1999 COMPLAINANT STATES HE IS BEING FORCED TO PAY ELECTRIC FOR TENANT WHILE THEY WILL NOT PAY RENTAL FEE AND STATE LAWS GIVE NO WAY TO COLLECT RENT & ELECTRIC COSTS ETS. IT IS TO COSTLY TO INSTALL EXTRA METER AND PAY HIGH RATE TO USE L ESS THAN $5.00 IN ELECTRIC IN 6 MONTHS.
U-00994296 Closed 2/8/1999 AGREEMENT DATED JANUARY 19, 1999, BETWEEN PP&L, INC. AND MONTOUR TOWNSHIP SUPERVISORS TO CONSTRUCT, OPERATE AND MAINTAIN ITS ELECTRIC LINE FACILITIES IN THE TOWNSHIP OF MONTOUR, COUNTY OF COLUMBIA.
C-00992204 Closed 2/8/1999 COMPLAINANT HAS A CONTRACT FOR INTERRUPTIBLE SERVICE THRU PP&L FOR OPTIONAL INTERRUPTIBLE SERVICE UNDER RATE SCHEDULE LP-5. THE CONTRACT PROVIDED THAT ELECTRIC POWER WOULD BE PROVIDED IN ACCORDANCE WITH RATE SCHEDULE LP-5. PP&L REPLACED ITS INTERRUPTIBLE POWER OPTION UNDER RATE SCHEDULE LP-5 WITH A NEW INTERRUPTIBLE POWER TARIFF KNOWN AS RATE SCHEDULE IS-T. RATE IS-T AUTHORIZES PP&L TO INTERRUPTIONS FOR ECONOMIC LOAD CONTROL, SYSTEM, AND LOCAL
A-110500F0279 Closed 2/10/1999 APPLICATION OF PP&L, INC., FOR APPROVAL OF THE TRANSFER BY SALE TO WOOD MODE INC., OF FACILITIES LOCATED IN KREAMER, SNYDER COUNTY, PENNSYLVANIA.
C-00992157 Closed 2/16/1999 COMPLAINANT STATES THEY ENTERED INTO A CONTRACT WITH PP&L ON 1/9/97 FOR IS-T OPTIONAL INTERRUPTIBLE SERVICE, IN WHICH PP&L WOULD PROVIDE ELECTRICAL POWER UNDER THIS SCHEDULE. SINCE 6/98 PP&L HAS CALLED FOR 10 ECONOMIC LOAD INTERRUPTIONS.
C-00992156 Closed 2/16/1999 COMPLAINANT ENTERED INTO A CONTRACT WITH PP&L, FOR OPTIONAL INTERRUPTIBLE SERVICE, UNDER RATE SCHEDULE LP-4. ON OCT 5, 1995 PP&L REPLACED LP-4 WITH IS-P. IS-P AUTHORIZES PP&L TO CALL INTERRUPTIONS FOR ECONOMIC LOAD CONTROL, SYSTEM AND LOCAL EMERGENCIES AND FOR TESTS OF A CUSTOMER'S ABILITY AND READINESS TO INTERRUPT LOAD DURING AN EMERGENCY. SINCE JUNE 1998 PP&L HAS CALLED 10 ECONOMIC LOAD INTERRUPTIONS.
Z-00552919 Closed 2/18/1999 COMPLAINANT CALLED PP&L FOR A PAYMENT ARRANGEMENT, THEY CALLED HER BACK TO SEE IF THEY WOULD REDUCE THE FIRST ARRANGEMENT. WHEN THEY DIDN'T THEY DIDN'T TELL HER THAT SHE HAS TO MAKE A PAYMENT EVERY TWO WEEKS. SHE WAS THEN TOLD IF SHE WANTED ON THE BUDGET SHE WOULD HAVE TO PAY $88 TO GET ON IT. SHE SAID SHE COULDN'T AFFORD IT. BUT SHE WOULD PAY $50 THAT IS ALL THAT SHE CAN AFFORD UNTIL IT'S ALL PAID OFF. IF SHE CAN AFFORD ANY EXTRA THEN SHE WILL SEND IT.
C-00992158 Closed 2/18/1999 COMPLAINANT STATES PP&L HAS HIM PAYING A BUDGET THAT IS HIGHER THAN NORMAL USAGE RATES. HE CALLED PP&L TO GET PUT ON A BUDGET PLAN AND HE WAS TOLD FLAT OUT NO. HE WOULD LIKE A FAIR BUDGET RATE.
C-00992162 Closed 2/19/1999 COMPLAINANT WOULD LIKE THE WEST COMPANY (MONTGOMERY FACILITY) FULLY INSTALLED INTO THE PP&L ENERGY PLUS PROGRAM (CHOICE PROGRAM). THE WEST COMPANY MONTGOMERY SITE BELIEVED THAT IT APPROPRIATELY ENROLLED IN THE PROGRAM FOR FULL PARTICIPATION IN 1999.

Showing results 3501 - 3525 of 11850

 

Need More Help?

If you can't find what you're looking for here, please contact the PA Public Utility Commission. Call us at 1-800-692-7380 or contact us online.

Document Search

Public utility documents available electronically include case dockets, public meeting orders and more.

Filing & Resources

Find utility-related reports, laws and regulations, federal filings, tariffs, procedures and more.

eFILING