Utility Code 110550
The Utility Detail View displays the Utility Information (identified by Utility Code - 110550), authorities, and case information associated with that utility.
Basic Utility Information
Utility Name
PECO ENERGY COMPANY-ELECTRIC
Utility Code
110550
Utility Type
Electric
Utility Status
Active
Carrier ID
Utility Contact Information
Physical Address
Mailing Address
2301 MARKET STREET
PHILADELPHIA PA 19101
Phone
Fax
Website
www.exeloncorp.com/
Utility Authorities Information
| Service Type | Authority Status | Date Certified | Suspension Date | Suspension Expiration | Application Number | Trading As Name |
|---|---|---|---|---|---|---|
| Electric Distributor | Active |
Utility Insurance Information
No insurance information for this utility.
EGS Territories Serviced by a Utility
Residential
No
Citizens’ Electric
No
Small Commercial
Duquesne Light
No
Mixed Meter
Met-Ed
No
Large Commercial
No
PECO
No
Industrial
No
Penelec
No
Governmental
No
Penn Power
No
Pike
No
PPL
No
UGI Utilities - Electric
No
Wellsboro
No
West Penn Power
No
Docketed Cases
| Docket Number | Case Status | Date Filed | Allegation |
|---|---|---|---|
| Z-01269740 | Closed | 3/10/2003 | COMPLAINANT STATES DOES NOT WHY HER BILL WAS SO HIGH. SHE IS ON THE CAP PROGRAM AND WOULD LIKE HER BILL TO STAY AT $55 MONTHLY LIKE IT IS NOW. |
| R-00038265 | Closed | 3/10/2003 | PECO ENERGY COMPANY HAS FILED SUPPLEMENT NO 47 TO ELECTRIC PA PUC NO 3, TO BECOME EFFECTIVE MAY 15, 2003, WHICH PROPOSES TO MODIFY INTERRUPTIBLE RIDER (IR-2) TO MAKE THIS RIDER PERMANENT AND INCORPORATE ENHANCEMENTS, WHICH WILL FACILITATE MORE DEMAND SIDE RESPONSE FROM THEIR CUSTOMERS. |
| Z-01254797 | Closed | 3/10/2003 | COMPLAINANT STATES SHE CAN NOT AFFORD THE PAYMENT THAT IS REQUESTED. SHE WANTS ASSISTANCE TO PAY THE BILL. |
| C-20039695 | Closed | 3/10/2003 | COMPLAINANT STATES SHE CAN NOT AFFORD THE PAYMENT REQUESTED. SHE WANTS TO MAKE AN ARRANGEMENT SHE CAN AFFORD. |
| C-20039697 | Closed | 3/10/2003 | COMPLAINANT STATES SHE CAN NOT AFFORD THE PAYMENT REQUESTED. SHE WANTS TO PAY $47 A MONTH PLUS $10 EXTRA. |
| C-20039694 | Closed | 3/10/2003 | COMPLAINANT STATES HE CAN NOT PAY THE BALANCE DUE BY 3/14/03. HE WANTS PUC TO GRANT THE BUDGET AMOUNT SET FORTH PREVIOUSLY. |
| C-20039693 | Closed | 3/7/2003 | COMPLAINANT STATES HE MADE PAYMENTS TO EXELON AND THEY WERE NOT APPLED TO HIS PECO BILL. HE WANTS PUC TO LOOK INTO THIS MATTER AND MAKE NECESSARY CORREC- TION. |
| C-20039686 | Closed | 3/7/2003 | COMPLAINANT STATES SHE CAN NOT PAY THE AMOUNT REQUESTED. SHE WANTS TO PAY $45 MONTHLY BUDGET PLUS $30 FOR ARREARS. |
| C-20039687 | Closed | 3/6/2003 | COMPLAINANT STATES THERE ARE CHARGES FROM EXELON ON HIS PECO BILL AND HE DID NOT AUTHORIZE ANOTHER SUPPLIER. HE WANTS THESE CHARGES REMOVED FROM HIS BILL. |
| C-20039692 | Closed | 3/6/2003 | COMPLAINANT STATES HER SERVICE IS GOING TO BE SHUT OFF. SHE WANTS PUC TO STOP THE SHUT OFF AND MAKE REASONABLE PAYMENT ARRANGEMENTS. |
| C-20039653 | Closed | 3/5/2003 | COMPLAINANT STATES SHE TRUSTED PAYMENTS WERE MADE BY A FAMILY MEMBER. SHE WANTS AND EXTENSION OF TIME TO PAY THE BILL IN FULL. |
| A-110550F0157 | Closed | 3/5/2003 | LETTER OF NOTIFICATION OF PECO ENERGY COMPANY, FILED PURSUANT TO 52 PA CODE CHAPTER 57, SUBCHAPTER G WITH RESPECT TO TRANSMISSION FACILITIES NEEDED FOR THE INTERCONNECTION OF FAIRLESS ENERGY LLC'S GENERATING FACILITIES - DIRECT CONNECTION, WORK RESIDENTIAL AREAS TO RECONDUCTOR AND RECONSTRUCT, BUILD AND MODIFY, ENTIRELY ON EXISTING RIGHT-OF-WAY AND FEE-OWNED LAND, APPROXIMATELY 3.9 MILES OF 138 KV TRANSMISSION LINE LOCATED IN BRISTOL TOWNSHIP, AND TO INCREASE THE VOLTAGE OF APPROXIMATELY 5.3 MILES OF TRANSMISSION LINE LOCATED IN BRISTOL TOWNSHIP, FALLS TOWNSHIP, TULLEYTOWN BOROUGH, HULMEVILLE BOROUGH, AND MIDDLETOWN TOWNSHIP. |
| A-110550F0156 | Closed | 3/5/2003 | LETTER OF NOTIFICATION OF PECO ENERGY COMPANY, FILED PURSUANT TO 52 PA CODE CHAPTER 57 SUBCHAPTER G WITH RESPECT TO TRANSMISSION FACILITIES NEEDED FOR THE INTERCONNECTION OF FAIRLESS ENERGY LLC'S GENERATING FACILITIES - DIRECT CONNECTION, WORK IN INDUSTRIAL AREAS TO RECONDUCTOR AND RECONSTRUCT, BUILD AND MODIFY, ENTIRELY ON EXISTING RIGHT-OF-WAY AND FEE-AND EASEMENT-OWNED LAND, APPROXIMATELY 4.6 MILES OF 138 KV TRANSMISSION LINE LOCATED IN FALLS TOWNSHIP. |
| C-20039688 | Closed | 3/5/2003 | COMPLAINANT STATES HE CAN NOT AFFORD PAYMENT. HE CAN PAY HIS BILL PLUS $15 PER MONTH. |
| A-110550F0158 | Closed | 3/5/2003 | LETTER OF NOTIFICATION OF PECO ENERGY COMPANY, FILED PURSUANT TO 52 PA CODE CHAPTER 57, SUBCHAPTER G WITH RESPECT TO TRANSMISSION FACILITIES NEEDED FOR THE INTERCONNECTION OF FAIRLESS ENERGY LLC'S GENERATING FACILITIES - SYSTEM SUPPORT WORK, TO RECONDUCTOR, AND RECONSTRUCT, BUILD AND MODIFY, ENTIRELY ON EXISTING TRANSMISSION LINE RIGHT-OF-WAY, APPROXIMATELY FOURTEEN (14) MILES OF 138 KV TRANSMISSION LINE LOCATED IN THE CITY OF PHILADELPHIA, BRISTOL TOWNSHIP AND BENSALEM TOWNSHIP, AND TO INCREASE THE VOLTAGE ON APPROXIMATELY SIX (6) MILES OF TRANSMISSION LINE LOCATED IN THE CITY OF PHILADELPHIA. |
| Z-01281241 | Closed | 3/3/2003 | COMPLAINANT STATES SHE CAN NOT PAY $226 PER MONTH. SHE WANTS TO PAY CURRENT CHARGES PLUS $25 ON ACCRUED BALANCE. |
| C-20039663 | Closed | 3/3/2003 | COMPLAINANT STATES SHE HAS ALWAYS BEEN ON A PAYMENT ARRANGEMENT BUT WHEN THEY RAISED HER PAYMENT FROM $60.00 TO $92.00. SHE STATES SHE WENT OFF THE PAY- MENT PLAN SINCE SHE COULD NOT AFFORD IT THEN SHE GOT BEHING. SHE WANTS TO BE PUT ON A PLAN TO PAY HER PREVIOUS BILL WITH AFFORDABLE ARRANGEMENTS. |
| C-20039628 | Closed | 2/28/2003 | COMPLAINANT STATES THAT SHE IS UNEMPLOYED AND HAVING PROBLEMS PAYING HER BILL SHE ASKS FOR A LOWER PAYMENT ARRANGEMENT. |
| C-20039627 | Closed | 2/27/2003 | COMPLAINANT STATES THAT SHE PAID ALL HER BILLS TO GREEN MOUNTAIN ENERGY WHEN SHE WAS SERVICED BY THEM. NOW PECO IS BILLING HER FOR $106.14 WHICH THEY SAY SHE OWED GREEN MOUNTAIN. SHE THINKS SHE WAS DOUBLE-BILLED AND WANTS THIS TO BE CLEARED. GREEN MOUNTAIN ENERGY COMPANY ADDED AS INDISPENSABLE PARTY. |
| C-20039626 | Closed | 2/27/2003 | COMPLAINANT BELIEVES HE WAS OVERCHARGED, BUT OFFERS TO PAY $100 A MONTH PLUS $15. |
| C-20039624 | Closed | 2/27/2003 | COMPLAINANT STATES THAT HE WAS PAYING $50 A MONTH, BUT THEN PECO READ HIS METER FOR 12 MONTHS AND HIS BILLS WENT UP. HE WANTS THE HIGH BILLS TO STOP. |
| C-20039625 | Closed | 2/27/2003 | COMPLAINANT STATES THAT SHE CANNOT PAY $1,102.11 BY MARCH 4, BUT OFFERS TO PAY THE ARRANGEMENT OF $218 PLUS $15. |
| C-20039623 | Closed | 2/26/2003 | COMPLAINANT BELIEVES THAT SHE WAS OVERCHARGED FOR AUGUST. SHE WANTS TO ARRANGE A REASONABLE MONTHLY PAYMENT AND ASKS FOR HELP. |
| C-20039619 | Closed | 2/25/2003 | COMPLAINANT BELIEVES THEY WERE OVERCHARGED BUT PECO ONLY REPLACED THE TRANS- FORMER. THEY WANT A REFUND FOR THE OVERCHARGES. |
| C-20039618 | Closed | 2/24/2003 | COMPLAINANT STATES THAT SHE CANNOT PAY THE AMOUNT ON HER BILL. SHE WANTS IT TO BE LOWERED AND PECO'S PRICES LOWERED. |
Showing results 7901 - 7925 of 13287
Need More Help?
If you can't find what you're looking for here, please contact the PA Public Utility Commission. Call us at 1-800-692-7380 or contact us online.
Document Search
Public utility documents available electronically include case dockets, public meeting orders and more.
Filing & Resources
Find utility-related reports, laws and regulations, federal filings, tariffs, procedures and more.
eFILING