Utility Code 110550
The Utility Detail View displays the Utility Information (identified by Utility Code - 110550), authorities, and case information associated with that utility.
Basic Utility Information
Utility Name
PECO ENERGY COMPANY-ELECTRIC
Utility Code
110550
Utility Type
Electric
Utility Status
Active
Carrier ID
Utility Contact Information
Physical Address
Mailing Address
2301 MARKET STREET
PHILADELPHIA PA 19101
Phone
Fax
Website
www.exeloncorp.com/
Utility Authorities Information
| Service Type | Authority Status | Date Certified | Suspension Date | Suspension Expiration | Application Number | Trading As Name |
|---|---|---|---|---|---|---|
| Electric Distributor | Active |
Utility Insurance Information
No insurance information for this utility.
EGS Territories Serviced by a Utility
Residential
No
Citizens’ Electric
No
Small Commercial
Duquesne Light
No
Mixed Meter
Met-Ed
No
Large Commercial
No
PECO
No
Industrial
No
Penelec
No
Governmental
No
Penn Power
No
Pike
No
PPL
No
UGI Utilities - Electric
No
Wellsboro
No
West Penn Power
No
Docketed Cases
| Docket Number | Case Status | Date Filed | Allegation |
|---|---|---|---|
| C-00871567 | Closed | 10/28/1987 | COMPLAINANT ALLEGES BILLING DISPUTE DUE TO CHARGE FOR MOVING ELECTRIC FACILI- TIES ON POLE NUMBER 25. |
| C-00913485 | Closed | 7/12/1991 | ALLEGING BILLING DISPUTE |
| C-00970937 | Closed | 10/29/1997 | COMPLAINANT STATES COMPANY DID NOT PROVIDE MONTHLY BILLING, FAILED TO PROVIDE DISCOUNT, AND WOULD LIKE THE COMPANY TO PROVIDE OUTSTANING AMOUNT TO REFLECT THE PROPER DISCOUNT |
| F-08432806 | Closed | 11/23/1984 | COMPLAINANT ALLEGES THAT SHE RECEIVED AN EXCESSIVE FINAL BILL FROM RESPONDENT. COMPLAINANT REQUESTS THE COMMISSION TO ISSUE AN ORDER PERMITTING RESPONDENT TO ISSUE COMPLAINANT A FINAL BILL FOR THE LAST BILLING PERIOD WHICH IS REASONABLE FOR ONE MONTHS USAGE BASED ON THE AVERAGE OF MONTHLY BILLS AND IN NO EVENT HIGHER THAN THE SINGLE HIGHEST MONTH OF BILLING FOR THE RESIDENCE IN QUESTION. |
| F-00355967 | Closed | 11/20/1997 | COMPLAINANT STATES APPLIED FOR THE CASH PROGRAM AND LIEHEAP PROGRAM AND RE- CEIVED THIS BUT COMPANY HAD CHANGED THE MONTHLY PAYMENT TO $110 INSTEAD OF $62 AND PAYMENTS ARE TOO HIGH. |
| P-00981473 | Closed | 8/20/1998 | PETITION OF PECO ENERGY COMPANY UNDER SECTION 56.118 OF TITLE 52 OF THE PENNSYLVANIA CODE FOR WAIVER FROM THE MEDICAL CERTIFICATION PROCEDURES AND FOR PERMISSION TO TERMINATE SERVICE TO RATEPAYER, RUTH PHILLIPS EVANS, WHO HAS NOT MET HER DUTY TO PAY UTILITY BILLS. |
| P-00840555 | Closed | 11/19/1984 | PETITION OF PHILADELPHIA ELECTRIC COMPANY TO TERMINATE SERVICE TO JIM AND LINDA SOMERS BY WAIVER OF MEDICAL CERTIFICATION PROCEDURES AT 52 PA. CODE, CHAPTER 56. |
| R-00811665 | Purged | 7/21/1981 | SUPPLEMENT NO. 19 TO GAS PA PUC NO. 24. MAKES CHANGES IN RULE 16 STANDARD PAYMENT TERMS TO REVISE AND REARRANGE FOR CLARITY VARIOUS PORTIONS OF THE RULE. |
| R-00821896 | Purged | 2/5/1982 | SUPPLEMENT NO. 23 TO TARIFF GAS PA PUC NO. 24. INCREASES THE RATE FOR GAS TRANSPORTATION SERVICE UNDER RATE TS. |
| U-00831076 | Purged | 8/22/1983 | AGREEMENT DATED AUGUST 2, 1983 BETWEEN THE PHILADELPHIA ELECTRIC COMPANY AND THE MONTGOMERY COUNTY SEWER AUTHORITY WHEREIN THE COMPANY GRANTS TO THE AUTHO- RITY THE RIGHT TO CONSTRUCT AND MAINTAIN AN INTERCEPTOR SEWER LINE WITHIN A TWENTY FOOT WIDE STRIP OF GROUND SITUATE IN PERKIOMEN TOWNSHIP, MONTGOMERY COUNTY. |
| S-00900052 | Closed | 8/2/1990 | SECURITIES CERTIFICATE OF PHILADELPHIA ELECTRIC COMPANY IN RESPECT OF CHANGE OR EXTENSION IN THE TERMS, CONDITIONS OR DATE OF 8.75% PREFERRED STOCK, PAR VALUE $100 PER SHARE. |
| S-00890915 | Closed | 1/31/1989 | SECURITIES CERTIFICATE OF PHILADELPHIA ELECTRIC CO. FOR THE ISSUANCE OF FIRST AND REFUNDING MORTGAGE BONDS OR UNSECURED DEBT IN THE FORM OF DEBENTURES OR NOTES, NOT IN EXCESS OF $350,000,000. |
| C-20042528 | Closed | 2/26/2004 | COMPLAINANT STATES HER BILLS ARE TOO HIGH. SHE WANTS PUC TO TRY TO GET COM- PANY TO LOWER THEIR RATES. |
| C-20078455 | Closed | 10/22/2007 | COMPLAINANT STATES THERE ARE INCORRECT CHARGES ON HIS BILL. |
| C-20077768 | Closed | 5/8/2007 | COMPLAINANT STATES SHE RECEIVED A NOTICE STATING THAT HER UTILITY SERVICE IS BEING TERMINATED AND SHE WOULD LIKE A PAYMENT AGREEMENT. |
| U-00890968 | Closed | 2/27/1989 | AGREEMENT DATED FEBRUARY 13, 1989 BETWEEN THE PHILADELPHIA ELECTRIC COMPANY AND THE TOWNSHIP OF WARMINSTER RELATIVE TO THE PUBLIC IMPROVEMENTS BEING CONSTRUCTED FOR THE NEW WARMINSTER 230-13 KV SUBSTATION ADJACENT TO COMPANY'S WARMINSTER SERVICE BUILDING SITUATE IN THE TOWNSHIP OF WARMINSTER, BUCKS CO. |
| Z-08567962 | Purged | 7/3/1980 | ALLEGING THAT EITHER COMPLAINANT'S METER IS FAULTY OR SOMEONE IS TAPPING COMPLAINANT'S ELECTRIC LINE, AND REQUESTING THAT RESPONDENT EITHER INSTALL A NEW METER OR INVESTIGATE THE POSSIBILITY OF TAPPING. |
| C-00003495 | Closed | 4/3/2000 | COMPLAINANT STATES ON 8/25/98 THEY CAME HOME AND FOUND THEIR AIR CONDITIONER HUMMING WITH NO FAN OPERATION. A PECO TECHNICIAN CAME AND SAID THAT THE VOLTAGE WAS LOWERED FOR THE PAST FEW DAYS AND IT WAS JUST PUT BACK ON LINE. THEY WERE TOLD THE REPAIR WAS UNDER THE $500 TARIFF LIMIT. SO THEY PROCEEDED WITH THE REMOVAL AND REPAIR ATTEMPTS. THEY REQUEST TO MEDIATE THIS MATTER. |
| A-110550F0151 | Closed | 9/18/2000 | JOINT APPLICATION FOR ISSUANCE OF CERTIFICATES OF PUBLIC CONVENIENCE AUTHORI- ZING THE SALE OF CERTAIN ASSETS, AND THE LEASE OF CERTAIN PREMISES, TO PJM INTERCONNECTION, LLC. (SEE ALSO A-110300F0093 FOR MET ED & PJM; A-110400F0039 FOR PENELEC & PJM; AND A-110500F0301 FOR PPL & PJM. A-110550F0151 IS FOR PECO AND PJM.)..................................................................... |
| P-00011883 | Closed | 3/29/2001 | LETTER-PETITION OF PECO ENERGY COMPANY REQUESTING APPROVAL OF AN AMENDMENT TO A SPECIAL CONTRACT FOR ELECTRIC SERVICE FOR THE UNIVERSITY OF PENNSYLVANIA PURSUANT TO RULE 4.6 OF PECO ENERGY'S ELECTRIC SERVICE TARIFF (PROPRIETARY AND NON-PROPRIETARY VERSIONS) |
| C-00004602 | Closed | 12/22/2000 | COMPLAINANT STATES PECO ENERGY HAS KNOWLEDGE ON TWO OCCASIONS OF A STOPPED METER AT THE CHURCH SITE PRIOR TO ITS ACTUAL REPLACEMENT, BUT FAILED TO CORR- ECT THE PROBLEM, A COMPANY REPRESENTATIVE INFORMED HIM OF THIS FACT. THERE- FORE THEY BELIEVE THAT THE ADJUSTED BILL FOR TWO YEARS OF ELECTRIC USAGE, WHICH IS NOW APPROXIMATELY $3,862.87 IS UNREASONABLE. THEY REQUEST THAT THE PUC ORDER PECO TO PROPORTION THIS ADJUSTED BILL OR IF POSSIBLE ELIMINATE IT ALTOGETHER. |
| C-20028173 | Closed | 7/16/2002 | COMPLAINANT STATES THAT SHE CANNOT PAY $52 A MONTH BECAUSE OF OTHER EXPENSES. SHE OFFERS TO PAY A BUDGET AMOUNT OF $30-35 A MONTH. |
| C-20028627 | Closed | 10/3/2002 | COMPLAINANT ALLEGES ELECTRIC BILL RAISED BECAUSE HE DOES NOT USE AN ELECTRIC HEAT PUMP AND REQUESTS PECO NOT BE ALLOWED TO USE TWO TIERED RATE SCALE. |
| Z-01320053 | Closed | 6/4/2003 | COMPLAINANT STATES SHE FEELS SHE IS NOT GETTING THE CORRECT READING FROM HER METER. SHE IS NOT EMPLOYED AND LOOKING FOR EMPLOYMENT. SHE WANTS TO BE PUT ON A BUDGET OF $100. THEN WHEN SHE GETS A JOB SHE WILL PAY MORE. |
| Z-01286230 | Closed | 5/5/2003 | COMPLAINANT STATES SHE CAN NOT AFFORD $600.00 A MONTH. COMPLAINANT WANTS PUC TO SET HER UP ON A BUDGET WITH TAKING INTO CONSIDERATION HER INCOME & OTHER BILLS. |
Showing results 7626 - 7650 of 13285
Need More Help?
If you can't find what you're looking for here, please contact the PA Public Utility Commission. Call us at 1-800-692-7380 or contact us online.
Document Search
Public utility documents available electronically include case dockets, public meeting orders and more.
Filing & Resources
Find utility-related reports, laws and regulations, federal filings, tariffs, procedures and more.
eFILING
Consumers, utilities and attorneys can save time by submitting documents to the PUC electronically.