Utility Code 110500
The Utility Detail View displays the Utility Information (identified by Utility Code - 110500), authorities, and case information associated with that utility.
Basic Utility Information
Utility Name
PPL ELECTRIC UTILITIES CORP
Utility Code
110500
Utility Type
Electric
Utility Status
Active
Carrier ID
Utility Contact Information
Physical Address
Mailing Address
TWO NORTH NINTH STREET
ALLENTOWN PA 18101
Phone
610-774-5696
Fax
610-774-4102
Website
www.pplweb.com
Email
KKLOCK@PPLWEB.COM
Utility Authorities Information
| Service Type | Authority Status | Date Certified | Suspension Date | Suspension Expiration | Application Number | Trading As Name |
|---|---|---|---|---|---|---|
| Electric Distributor | Active | A-110500 | PPL UTILITIES (PPL) |
Utility Insurance Information
No insurance information for this utility.
EGS Territories Serviced by a Utility
Residential
No
Citizens’ Electric
No
Small Commercial
Duquesne Light
No
Mixed Meter
Met-Ed
No
Large Commercial
No
PECO
No
Industrial
No
Penelec
No
Governmental
No
Penn Power
No
Pike
No
PPL
No
UGI Utilities - Electric
No
Wellsboro
No
West Penn Power
No
Docketed Cases
| Docket Number | Case Status | Date Filed | Allegation |
|---|---|---|---|
| Z-23176085 | Purged | 12/9/1980 | ALLEGING THAT RESPONDENT IS THREATENING TO TERMINATE SERVICE AND REQUESTING AN EXTENSION OF 1 TO 2 MONTHS TO ATTEMPT TO PAY BILL. |
| U-00994352 | Closed | 6/9/1999 | AGREEMENT DATED MAY 7, 1999, BETWEEN PP&L, INC., AND THE FRACKVILLE AREA MUNI- CIPAL AUTHORITY, WHEREBY THE COMPANY GRANTS THE AUTHORITY A 20-FOOT WIDE SEWER EASEMENT (0.28 ACRE) ON A PORTION OF PP&L'S FRACKVILLE LINE CREW QUARTERS PROPERTY SITUATE IN WEST MAHANOY TOWNSHIP, SCHUYLKILL COUNTY, PENNSYLVANIA. |
| Z-00685219 | Closed | 1/4/2000 | COMPLAINANT STATES WHEN CALLED TO MAKE ARRANGEMENTS FOR HER PAST DUE ELECTRIC BILL, HER HUSBAND HAD BEEN OFF WITH PNEUMONIA, AND SINCE THEN HAS BEEN LAID OFF. SHE DOESN'T MIND THE BUDGET PLAN BUT $45 IS TOO HIGH FOR THEIR BUDGET. WOULD LIKE THE AMOUNT THEY HAVE TO PAY LOWERED, STATES THEY CAN'T AFFORD $45 OVER THEIR BUDGET PLAN. |
| Z-00721395 | Closed | 5/8/2000 | COMPLAINANT STATES ON 12/3/99 HE PHONED PP&L TO ARRANGE TO PAY OFF AN UNPAID BALANCE OF APPROXIMATELY $400. THEY AGREED THAT HE WOULD PAY HIS CURRENT CHARGES EVERY MONTH PLUS $40 UNTIL THE BALANCE WAS PAID OFF. ABOUT A WEEK LATER HE RECEIVED A NEW BILL FROM PP&L DATED 12/6/99 FOR $119.88. HE ASSUMED THAT AFTER THIS WAS THREE DAYS AFTER TALKING TO PP&L HE THOUGH THIS REFLECTED THE AGREEMENT. ON 1/8/00 HE RECEIVED A NOTE FROM PP&L TO PAY AN OUTSTANDING BALANCE OF $120. HE FEELS THAT THIS IS UNFAIR, BECAUSE HE HAS KEPT TO THE AGREEMENT AS HE UNDERSTOOD IT. HE WANTS PP&L TO HONOR THEIR ORIGINAL AGREE- MENT OF 12/3/99, THAT HE WILL PAY HIS CURRENT BILL PLUS $40 EVERY MONTH UNTIL HIS BALANCE IS PAID OFF. |
| C-20016037 | Closed | 8/16/2001 | COMPLAINANT STATES THAT THEY HAVE BEEN OVERCHARGED BY PPL. HE STATES THAT THEY USE 2 OFFICES IN A VACANT BUILDING. WHEN THEY NOTIFIED PPL, THEIR BILLS CAME DOWN DRASTICALLY. THEY WANT THE PUC TO MAKE PPL JUSTIFY THE HIGH BILLS AND PROVE THAT THEY HAD ACTUALLY USED AN ENORMOUS AMOUNT OF ELECTRICITY. THEY ALSO WANT THE PUC TO INVESTIGATE WHY THEIR BILLS CAME DOWN, WITHOUT ALT- ERING THEIR USAGE. |
| R-00016986 | Closed | 12/14/2001 | PPL ELECTRIC UTILITIES CORPORATION HAS FILED SUPPLEMENT NO 20 TO TARIFF ELECTRIC PA PUC NO 201, TO BECOME EFFECTIVE FEBRUARY 12, 2002, WHICH PROPOSES CHANGES TO RULE 3 OF PPL ELECTRIC'S TARIFF TO ADD LANGUAGE PERMITTING A CUSTOMER TO ELECT TO MAKE A ONE-TIME PAYMENT IN LIEU OF ANNUAL DIFFERENTIAL BILLINGS DURING THE PERIOD OF ALINE EXTENSION REVENUE GUARANTEE. |
| Z-01072146 | Closed | 3/11/2002 | COMPLAINANT STATES THAT SHE PLANS TO PAY OFF HER DEBT AND DOES NOT WANT TO BE DISCONNECTED. SHE ALSO ASKS FOR REFERRALS FOR HELP. |
| C-20027422 | Closed | 4/8/2002 | COMPLAINANT STATES THAT HE HAS RECORDS OF PPL COLLECTING SALES TAX SINCE 1998 HE BELIEVES THE CHARGE IS ILLEGAL AND WANTS REIMBURSED. HE ALSO WANTS A COM- PLETE BILLING HISTORY. |
| C-00913237 | Closed | 2/6/1991 | COMPLAINANT REQUESTS REVISED PAYMENT SCHEDULE. |
| C-00968944 | Closed | 12/26/1996 | COMPLAINANT STATES THAT THE RESPONDENT TOLD HER THAT HER RESIDENCE PROBABLY HAD A FOREIGN LOAD WHICH SHE SAID WAS TOLD TO HER VERBALLY AND IN WRITING WHICH THEY HAVE NOT HONORED. THE COMPLAINANT WANTS A MORE EQUITABLE DECISION UNDER THE CIRCUMSTANCES AND IS ALSO STATING THAT THE INVESTIGATION REPORT IS NOT TOTALLY CORRECT IN ITS STATEMENTS. |
| F-08216883 | Purged | 8/25/1982 | ALLEGING ERRONEOUS BILLINGS FOR SUMMER RESIDENCE, AND REQUESTING INVESTIGA- TION. |
| R-00811636C0005 | Purged | 1/20/1982 | ALLEGING RATES UNFAIR,UNJUST,UNREASONABLE ETC. |
| S-00980670 | Closed | 3/19/1998 | SECURITIES CERTIFICATE OF PENNSYLVANIA POWER & LIGHT COMPANY FOR THE ISSUANCE OF FIRST MORTGAGE BONDS IN A PRINCIPAL AMOUNT NOT TO EXCEED $200 MILLION. |
| U-00850200 | Closed | 10/28/1985 | AGREEMENT DATED OCTOBER 21, 1985 BETWEEN THE PENNSYLVANIA POWER & LIGHT CO. AND THE COUNTY OF MONTGOMERY WHEREIN THE COUNTY GRANTS TO THE COMPANY THE RIGHT TO CONSTRUCT, OPERATE, MAINTAIN AND REPAIR ONE (1) POLE AND OVERHEAD WIRES SITUATE ON THE SOUTH SIDE OF MONTGOMERY AVENUE IN UPPER HANOVER TWP., MONTGOMERY COUNTY REQUIRED TO PROVIDE NEW ELECTRIC SERVICES TO GEORGE HYAM. |
| C-00812705 | Purged | 10/19/1981 | ALLEGING THAT THE INSTALLATION OF A DEMAND METER IN COMPLAINANT'S RESIDENCE IS DISCRIMINATORY BECAUSE OF THE LARGE NUMBER OF FAMILY MEMBERS AND REQUESTING THAT RESPONDENT BE REFRAINED FROM INSTALLING METER UNTIL A HEARING IS HELD. |
| F-01590245 | Closed | 4/15/2004 | COMPLAINANT STATES THAT HE CALLED TO TELL PPL HE WAS MOVING BUT THEY DID NOT TERMINATE HIS ELECTRICITY AND CLAIM HE NEVER CALLED. HE DOES NOT WANT TO BE RESPONSIBLE FOR THE BILL. |
| U-00045075 | Closed | 8/6/2004 | AGREEMENT DATED JULY 28, 2004 BETWEEN PPL ELECTRIC UTILITIES CORPORATION AND THE CITY OF ALLENTOWN, RELATIVE WITH THE RIGHT TO CONSTRUCT, OPERATE AND MAINTAIN ITS ELECTRIC LINE FACILITIES IN THE CITY OF ALLENTOWN, COUNTY OF LEHIGH, COMMONWEALTH OF PENNSYLVANIA. |
| C-20077349 | Closed | 2/7/2007 | COMPLAINANT STATES HIS COMPLAINT IS PPL'S BILLING ERROR IN WHICH PPL IS AT FAULT. HIS RECOMMENDATION IS THAT HE PAYS 50% OF THE BALANCE AND PPL PAYS THE OTHER 50%. |
| C-20077987 | Closed | 7/9/2007 | COMPLAINANT STATES HE RECEIVED A NOTICE THAT HIS UTILITY SERVICE IS BEING TERMINATED. HE STATES ALL THEY HAD TO DO WAS ASK HIM TO PAY MORE ON HIS BILL, WHICH HE WAS GOING TO DO. |
| U-00901334 | Closed | 6/4/1990 | AGREEMENT DATED MAY 22, 1990, BETWEEN PENNSYLVANIA POWER AND LIGHT COMPANY AND SOUTH HANOVER TOWNSHIP WHEREBY THE TOWNSHIP GRANTS TO THE COMPANY THE RIGHT TO CONSTRUCT AND MAINTAIN ELECTRIC LINE FACILITIES BETWEEN SOUTH HANOVER STREET AND THE SWATARA CREEK IN SOUTH HANOVER TOWNSHIP, DAUPHIN COUNTY, REQUIRED IN CONNECTION WITH THE UNION DEPOSIT CONVERSION. |
| U-00880860 | Closed | 9/12/1988 | RESOLUTION DATED AUGUST 25, 1988 OF THE CITY OF HARRISBURG PERMITTING PENNSYL- VANIA POWER & LIGHT COMPANY TO CONSTRUCT AND MAINTAIN ONE SUBMERSIBLE TRANS- FORMER AND APPURTENANCES ON PROPERTY SITUATE ON CITY ISLAND, CITY OF HARRIS- BURG, DAUPHIN COUNTY. |
| U-00962970 | Closed | 3/7/1996 | AGREEMENT DATED DECEMBER 20,1995, BETWEEN PENNSYLVANIA POWER & LIGHT COMPANY AND DERRY TOWNSHIP MUNICIPAL AUTHORITY (DTMA), WHEREBY THE COMPANY GRANTS THE AUTHORITY A THIRTY (30) FOOT WIDE EASEMENT FOR THE INSTALLATION OF A SEWER LINE UNDER AND THROUGH COMPANY-OWNED PROPERTY SITUATE IN DERRY TOWNSHIP, DAUPHIN COUNTY, PENNSYLVANIA. |
| Z-00300673 | Closed | 1/29/1996 | COMPLAINANT REQUESTS HER MONTHLY PAYMENTS BE LOWERED. INSUFFICIENT IN COME. |
| Z-00259270 | Closed | 12/22/1994 | COMPLAINANT WOULD LIKE A LOWER MONTHLY BUDGET. |
| Z-00335466 | Closed | 11/14/1996 | REQUEST PAYMENT ARRANGEMENTS. |
Showing results 6026 - 6050 of 11733
Need More Help?
If you can't find what you're looking for here, please contact the PA Public Utility Commission. Call us at 1-800-692-7380 or contact us online.
Document Search
Public utility documents available electronically include case dockets, public meeting orders and more.
Filing & Resources
Find utility-related reports, laws and regulations, federal filings, tariffs, procedures and more.
eFILING
Consumers, utilities and attorneys can save time by submitting documents to the PUC electronically.